South Chatham Park Way

Project Overview Video

 

Project History

The alignment of Project R-5963 was initially studied as part of a feasibility study in 1994. Since then, similar alignments have been included in various local plans including the Chatham County 2017 Comprehensive Plan, Plan Chatham and the Pittsboro 2015 Comprehensive Transportation Plan with a revised northern terminus of U.S. 15-501. 

A second feasibility study was completed in 2019 to evaluate a new road from U.S. 15-501 south of Pittsboro to U.S. 15-501 north of Pittsboro utilizing the existing section of Chatham Park Way between U.S. 64 Business and U.S. 64 Bypass. The route was funded as two separate projects: R-5930 (the northern section) and R-5963 (the southern section). 

Project Description and Highlights

The proposed project, State Transportation Improvement Program (STIP) Project No. R-5963, begins at U.S. 15-501 south of Pittsboro and ends at U.S. 64 on the east side of Pittsboro. This project, also referred to as South Chatham Park Way, will build a 3.3-mile road on new location from U.S. 15-501 to U.S. 64 Business, and will widen the existing 1.1-mile roadway from U.S. 64 Business to U.S. 64. Together with the North Chatham Park Way (NCDOT Project R-5930), this project will complete an eastern loop around downtown Pittsboro. The project is intended to provide an alternate route for traffic traveling through downtown Pittsboro while continuing to support the economic development of the region. It will increase mobility options for drivers, bicyclists, and pedestrians.​

 

The project has been divided into 4 phases (A-D) for construction.

Phase A:   U.S. 15-501 south of Pittsboro to Moncure-Pittsboro Road

Phase B:   Moncure-Pittsboro Road to U.S. 64 Business

Phase C:   Widening of existing, Chatham Park Way from U.S. 64 Business to just north of U.S. 64

Phase D:   Cconstruction of a new westbound on-ramp from Chatham Park Way to U.S. 64 and realignment of Suttles Road to a new intersection with Chatham Park Way

 

The preferred alternative:

  • Together with North Chatham Park Way (NCDOT Project R-5930), this project will complete an eastern loop around downtown Pittsboro.
  • Will provide an alternate route for traffic traveling through downtown Pittsboro.
  • May continue to support the economic development of the region.
  • Will increase mobility options for drivers, bicyclists, and pedestrians.​

Preferred Alternative Project Design Maps 

Clicking on the links below will open the maps in a new window for viewing or downloading.

U.S. 15-501 to West of Moncure-Pittsboro Road

West of Moncure Pittsboro Road to Roberson Creek Area

Roberson Creek Area to North of U.S. 64 Business

U.S. 64 Business to existing Chatham Park Way (Relocate Suttles Road connection to Chatham Park Way)

Proposed Typical Sections

Roadway - U.S. 15-501 south of Pittsboro to future Industrial Park Drive

This section will contain:

  • one through lane in each direction separated by a median (width varies)
  • curb and gutter on the inside (framing median)
  • a 4-foot outside paved shoulder and 3-foot unpaved
  • a 10-foot multiuse path on each direction separated from traffic by a 13.5 foot median*

* Multiuse paths shown are preliminary and subject to a municipal agreement with the Town of Pittsboro.

 


Bridge west of Moncure-Pittsboro Road

Bridge will contain

  • one through lane in each direction separated by an 11.5 foot raised concrete median
  • an 11.5 foot wide multiuse path on both sides


Roundabout at Moncure-Pittsboro Road

A roundabout is planned at the Moncure-Pittsboro Road intersection, as shown on Map 2 linked above. The roundabout will have one travel lane around the circle, and the multiuse path will cross all four roadway legs. 

 

Roadway - future Industrial Park Drive to U.S. 64

This section will contain:

  • two through lanes in each direction separated by a median (width varies)

  • curb and gutter on both sides of roadway

  • a 10-foot multiuse path on each direction separated from traffic by a 6.5-foot median*

* Multiuse paths shown are preliminary and subject to a municipal agreement with the Town of Pittsboro.

 

 


Bridge Over Roberson Creek

Bridge will contain

  • two bridges separated by 11.5 feet 

  • two through laneson each bridge 

  • an 11.5-foot wide multiuse path on both sides


Bridge Widening North of Wendover Parkway

Bridge will contain

  • 2 through lanes in each direction 

  • an 11.5-foot multiuse path on both sides

  • a 6-foot raised concrete median

  • Southbound section of bridge will also contain a right lane for turns onto Wendover Parkway and 2 left turn lanes onto future Wendover Parkway

 


Bridge Widening Over U.S. 64

A new bridge will be built to the east of the existing bridge. After it is built, existing northbound traffic will be moved from the existing bridge to the new bridge, and the existing bridge will carry two lanes of southbound traffic instead of one. The bridge extension will contain

  • 2 through lanes
  • a 10.4 foot raised concrete median on the inside which combined with existing bridge will create an 11.5-foot area between directions of travel
  • an 11.5-foot multiuse path 

Project Funding

Project R-5963 is listed in the currently adopted State Transportation Improvement Program (STIP).

 

Estimated Amount*

Development & Design

$  9.6 Million

Right-of-Way Acquisition

                 N/A 

Construction Costs

Phases A and B

Phase C

Phase D

 

$  65.6 Million

$  32.1 Million

$    6.7 Million

Total Cost

         $ 114  Million

* Estimated costs are preliminary and subject to change

Costs shown are rounded

Project Timeline

 

Milestone

Date*

Environment Document 

March 2023

Right-of-Way Acquisition Begins

N/A

 

Construction Begins

Phase A

Phase B

Phase C

Phase D

April 2024

March 2025

March 2025

TBD**

April 2024 

* Schedule is preliminary and subject to change

** Section C will be rescored during the upcoming round of STIP development

Project Comments

NCDOT accepts comments throughout all phases of project development.  

All comments will be taken into consideration, and carry equal weight, regardless of submittal method.

To submit comments for consideration during the current phase of project development,

please submit before NEED DATE


The public is encouraged to leave comments using this webpage, email, or phone number:

or mailed to the project contacts at the addresses listed below.

Email: South-Chatham-Park-Way@PublicInput.com 

Phone Number: 984-205-6615      enter project code 2966 to leave a message

Question title

Would you like to be added to the project email list?

Question title

Need question for each 'typical' and phase.

Project Contact

 Jeffrey Stroder

NCDOT Division 8

Division Project Manager

121 DOT Drive

Carthage, NC 28327

Project Contact

 Vance Blanton

Kimley-Horn

Consultant Project Manager

421 Fayetteville Street, Suite 600

Raleigh, NC 27601

Title VI Feedback

To ensure we’re hearing from a broad set of voices, would you be willing to share (completely anonymously) some information about yourself?

If so, please click here: https://publicinput.com/NCDOT-Title-VI

RESOURCES FOR PROPERTY OWNERS 


Although the N.C. Department of Transportation works to minimize the number of homes and businesses displaced by a road project, it is inevitable, in many cases, that a certain amount of private property is needed. The following information explains right of way acquisition and answers questions about the process.  

     
Right-of-Way Brochure Single Page Layout      Folleto del Proceso de Adquisición de Bienes Raíces
Right-of-Way Frequently Asked Questions

Right of way Acquisition Process Videos

English                                                                     Spanish