Project Highlights

The purpose of the proposed project is to provide a route to redirect large truck traffic onto Greene Street from the existing U.S. 1, which connects to downtown Rockingham. The proposed project is needed to address the large amount of truck traffic along U.S. 1.

The project proposes to make improvements to S.R. 1516 (Greene Street) from U.S. 220 to the existing U.S. 1 by:

  • Widening and upgrading Greene Steet to include curb and gutter and sidewalks
  • Realign Greene Street to become part of U.S. 1
  • Upgrade the existing intersection of Greene Street and U.S. 1 

 

Project History

A virtual public meeting was held in March 2021, with a subsequent affected property owners meeting held in-person at the project site in August 2021.

Since August 2021, the design was revised from a roundabout at the existing intersection of Greene Street and U.S. 1 to a T-intersection to reduce potential impacts to private properties and the surrounding historic district.

In May 2022 and July 2022, the design team was able to get concurrence from the State Historic Preservation Office with some additional right of way changes.

The revised design is available on the project website for public review and comment. 

Public Involvement

Information will be provided to the public in a virtual format on this website. The public is encouraged to provide comments or share their thoughts regarding the proposed concept below

Comments were due by Sept. 16, 2021

 

Click here for updated map 2022.

U-6027-Public meeting map_Greene_St_East_of_Caroline_St_to_US1

Typical Sections

Typical 1 (4-lane with curb and gutter and a sidepath on both sides) is Greene Street from US 220 to N. Lee Street.

 

 

 

 

Typical 2 (2-lane with curb and gutter and sidepath on one side and sidewalk on the other side) is Greene Street from N. Lee Street to US 1.

 

 

 

 

Videos:

Project Overview Video

 

 

 

How to Read a Public Meeting or Hearing Map:

A video explaining how to read a public hearing or meeting map can be viewed below. The video contains information on colors used and symbology.

 

 

Roundabouts in North Carolina

 

Project Funding

This project is listed as Project U-6027 in the N.C. Department of Transportation’s State Transportation Improvement Program (STIP) and is funded for $8.05 million.  

 

 Activity

 Estimated Amount*

  Project Development & Design

$ 650,000

  Property Acquisition

$1,200,000

  Utility Relocation 

$ 500,000

  Construction Costs

$5,700,000

  Total Cost

$8,050,000**

* Estimated amounts are subject to change. Based on NCDOT STIP.

** Total Cost includes approximately $650,000 in previous year spending.

 

Project Timeline

 Milestone

    Date*

  Public Meeting and Comment Period

March 2021

 Additional Public Comment Period 

 August 2022

 Complete Environmental Document

 August 2022

 Right-of-way Acquisition Begins

FY 2023

 Construction Begins

FY 2025

* Future dates are preliminary and subject to change

Project Comments:

All comments will be taken into consideration, regardless of submittal method.

Comments were submitted by September 16, 2021.  

 

Question title

Would you like to be added to the project email list?

Question title

Do you have any comments or concerns about potential property impacts? Please be specific.

Closed for Comments

Question title

Please share any additional comments about the project.

Closed for Comments

  PROJECT CONTACT INFORMATION 

Greg Davis

Project Engineer

NCDOT Highway Division 8

121 DOT Drive

Carthage, NC  28327

 

  PROJECT CONTACT INFORMATION 

Tim Goins

Project Consultant

VHB

940 Main Campus Drive, Suite 500

Raleigh, NC  27606

        

 

RESOURCES FOR PROPERTY OWNERS 

 

Although the N.C. Department of Transportation works to minimize the number of homes and businesses displaced by a road project, it is inevitable, in many cases, that a certain amount of private property is needed. The following information explains right of way acquisition and answers questions about the process.  

     
Right-of-Way Brochure Single Page Layout      Folleto del Proceso de Adquisición de Bienes Raíces
Right-of-Way Frequently Asked Questions

Right of way Acquisition Process Videos

English                                                                     Spanish